Kunle Elizah Ogundipe, Clinton Aigbavboa, Babatunde Fatai Ogunbayo (2024). Validating critical factors affecting national safety incentives policy for the construction industry in developing countries. In: Sustainable Construction in the Era of the Fourth Industrial Revolution. AHFE Open Access, vol. 149, pp. 50–61. https://doi.org/10.54941/ahfe1005274
cidb Centre of Excellence & Sustainable Human Settlement and Construction Research Centre, Department of Construction Management & Quantity Surveying, University of Johannesburg, South Africa ↗
A national safety incentive policy is a mix of policy instruments and strategies outlining the rules, templates, and standard procedures for designing and implementing safety incentives within a country. Through a Delphi study, this study assesses critical factors affecting the development of a national safety incentives policy for the construction industry in developing countries using Nigeria as a case study. A qualitative technique was adopted using the Delphi technique to select a representative sample of expert panellists for the study. The Delphi findings indicate fifteen (15) identified factors affecting the development of a national safety incentives policy in Nigeria. Of these fifteen (15) identified factors, six (6) had a very high impact (VHI: 9.00 – 10.00), four (6) had a high impact (HI: 7.00 - 8.99), and the remaining three (3) factors recorded a medium impact (MI: 5.00 - 6.99). The study's key findings reveal that the leading critical factors affecting developing countries, including Nigeria, in developing a national safety incentives policy include weak institutional framework, occupational safety and health agency’s corrupt practices, stakeholders’ absence in policy development, insufficient government budget for occupational safety and health agency, ineffective H&S code of practice, absence of national safety incentive vision, political influence on occupational safety and health enforcement agency, inadequate regulatory framework, ineffective occupational safety and health policy enforcement, and ineffective occupational safety and health policies. This study concluded by calling for a standalone national safety incentive policy that will holistically support the implementation of safety incentives within the construction industry.
Employees’ and employers’ commitment towards improving workplace safety behaviour and performance is one of the most significant challenges facing the construction industry in developing countries (Ogunde et al., 2017; Ogundipe et al., 2018; Ahmed et al., 2021). According to Ahmed and Faheem (2021), the need to improve safety behaviour as a strategy of total
Validating Factors Affecting a National Safety Incentives Policy 51
safety management has become dominant in developing countries. How- ever, construction organisations use various motivations, particularly safety incentives, to align employees with performance goals such as safety, qual- ity, cost, and productivity (Alfandi and Alkahsawneh, 2014; Ogwueleka, 2015; Ogundipe et al., 2023a). The application of safety incentives has transformed various operations of the construction industry. Goodrum and Gangwar (2004), Zulkefli et al. (2014) and Ogundipe et al. (2023b) noted that the safety incentives concept is rooted in the demands to align employ- ees with organisation performance-related goals, improve workplace safety behaviour, and share risk between clients and contractors. This is because the incentive concept is often based on various motivation theories explain- ing what drives human behaviour and why people need change over time (Hilmarsson & Rikhardsson, 2011). Gerhart (2017) maintained that safety incentives promote safe behaviours that can reduce destructive behaviours that could hinder attaining projects, clients, and organisational goals and improve workers’ performance. Safety incentives allow organisations to use financial or non-financial payments to motivate workers outside their wages in line with their set standards for individuals or groups of workers to enhance their performance (Tongo, 2011; Zulkefli et al., 2014). Hence, safety incentives drive workers beyond their actual performance due to extrinsic and intrinsic rewards (Hilmarsson and Rikhardsson, 2011; Oloke et al., 2017).
Choi et al. (2012) observed that despite the Hong Kong government’s intervention and introduction of safety incentives (pay-for-safety schemes) in public works construction contracts, there are still notable challenges due to ineffective policy implementation and administrative processes. Equally, in Iran, Ghasemi et al. (2015) attributed critical factors affecting national safety incentive policy (NSIP) to the lack of policy development, conflict- ing government policies, and lack of annual review and evaluation of safety incentive policy. The Tanzania government’s pay and incentive policy also allows organisations to operate unified and transparent incentive schemes, facilitate appropriate rewards and sanctions towards acceptable performance standards, and plan and control employees’ wages, but most organisa- tions’ management lacks commitment and inadequate communication in implementing incentive policies (Kiguhe, 2013). Nonetheless, Dambisya and Dambisya (2007) maintained that the incentive policies are often applicable in developing Eastern and Southern African countries comprising financial and non-financial incentives to improve employee training and career path development, social needs support, workplace conditions, access to health care, and financial-related salary enhancement and allowances.
Unfortunately, the position of safety incentives in developing countries shows its impact is limited due to ineffective or non-availability of health and safety policies, weak enforcement frameworks, lack of safety incentives reg- ulations and policies, budgetary allocation planning, and limited resources (Eyiah et al., 2019; Boadu et al., 2020; Boadu et al., 2021; Ogundipe et al., 2023c). Armstrong and Taylor (2014) and Ahmed and Faheem (2021) posited that policies and legislation are necessary to sustain employees’ com- mitment to workplace safety practices and improve performance and pro- ductivity. Furthermore, Wilde (2011) and Jiang et al. (2019) highlighted that
factors such as policies guiding goal setting and performance indicators affect the construction industry’s design of safety incentive schemes in developing countries. Thus, the safety incentive policy allows construction organisations to improve H&S performance by focusing on proactive approaches rather than reactive measures (Laitinen et al., 2013; Haas and Yorio, 2016). Kheni and Braimah (2014) and Boadu et al. (2021) attributed the critical factors affecting the Ghanaian construction industry to the non-availability of com- prehensive health and safety policies to address safety incentive design and implementation. The non-availability in Ghana translates into the absence of a national safety incentive vision, weak institutional framework, the political influence of the OSH enforcement agency, ineffective logistics for the OSH agency, the OSH enforcement personnel skills shortage, and ineffective H&S code of practice (Kheni and Braimah, 2014; Boadu et al., 2021). Likewise, Iipinge (2009) asserted that developing NSIP in developing countries is often affected by inadequate regulatory frameworks, the absence of stakeholders in policy development organisations’ management authority, decisions, and the allocation of available resources. According to Ditlopo et al. (2013), incentive policy implementation in the Republic of South Africa has been limited due to bad governance, inadequate regulatory framework, inadequate resources to meet the policy pre-conditions, inaccurate public sector human resource database, and inaccurate and incomplete documentation from enforcement agencies.
Hence, it is essential to address the gap in knowledge of the critical fac- tors affecting the NSIP development, which could significantly influence the effective design and implementation of safety incentives in the Nigerian con- struction industry. This study examines expert opinions on critical factors affecting the development of a national safety incentive policy in the con- struction industry in developing countries, using Nigeria as a case study to enrich its application among construction organisations within the Nigerian construction industry. Therefore, this study intends to provide answers to the following research Delphi forecasted questions:
Will a national safety incentives policy ever be developed for the Nigerian construction industry?
What is the likely timeframe for adopting safety incentive schemes within the Nigerian construction industry?
Does the lack of a national safety incentive policy for construction organi- sations affect the Nigerian construction industry’s effective H&S practices and employee motivation drives?
What are the critical factors affecting the NSIP development in the Nigerian construction industry?
METHODOLOGY
This study adopted the Delphi approach in validating critical factors affecting the NSIP development in the construction industry in developing countries, using expert panellists in Nigeria as a case study. According to Nasa et al. (2021), the Delphi method is a structured technique developed through inter- action, forecasting, and communication within a group of experts dealing
Validating Factors Affecting a National Safety Incentives Policy 53
with a complex research problem. Ikuabe et al. (2023) noted that the Delphi technique allows researchers to explore philosophical and qualitative stances in deducing a constructive perspective in research. Mahamadu et al. (2019) and Ikuabe et al. (2023) described the Delphi technique as the formation of distinctive knowledge and understanding of the world emanating from expe- riences and contemplation of those experiences. The Delphi process is based on the anonymous views of experts pooling experiences and intelligence to improve individual judgment views on a research problem (Ameyaw et al., 2016; Ikuabe et al., 2023). To begin with, an extant literature review was conducted to identify criti- cal factors affecting the NSIP development in developing countries before the Delphi iteration. Given this, expert opinions on the identified critical factors were validated through the Delphi technique. However, in determining rep- resentative sample size for a Delphi study, existing literature suggests that no general rule applies to sample choice selection (Howell and Kemp, 2005; Ameyaw et al., 2016). Nonetheless, the selection criteria adopted in this study include expert panellists meeting a minimum of bachelor’s degree aca- demic qualifications in the built environment disciplines (Giel and Issa, 2016; Evans and Farrell, 2021); have a minimum of five years of working experi- ence (Chan et al., 2001; Ikuabe et al., 2023). Likewise, the selected expert panellists demonstrate theoretical knowledge and practical experiences of safety incentives and H&S practices from academics and professional prac- tice (Aigbavboa, 2014; Evans and Farrell, 2021; Ogunbayo et al., 2023). Thus, twenty-five experts were invited via e-mails to participate in the Delphi study, and a copy of their curriculum vitae was requested. Twenty-one met the required selection criteria, but fifteen experts completed and returned the first round of the Delphi questionnaire within the set time frame and were involved in the entire Delphi study process.
Likewise, the expert panellists’ consensus at each round of the Delphi pro- cess was based on the relative impact index (RII) in validating critical factors affecting the NSIP development in the construction industry. The expert pan- ellists’ decision to reach a consensus is based on a 10-point impact scale in which 1 to 2 represents no impact (NI), 3–4 represents low impact (LI), 5–6 represents medium impact (MI), 7–8 represents high impact (HI), and 9–10 represents very high impact (VHI). This involves the determination of Median (M), mean (x), standard deviation (σx), and interquartile deviation (IQD) to calculate and analyse each round of the Delphi process for reaching consensus in this study:
Weak consensus - median ≤6.99, mean ≤5.99, and IQD ≥2.1≤3 and ≤59% (5.99).
Good consensus - median 7-8.99, mean 6-7.99, IQD ≥1.1≤2 and ≥60%≤79% (6-7.99); and
Strong consensus - median 9-10, mean 8-10, IQD ≤1 and ≥80% (8-10).
However, the reliability and interrelatedness of the data obtained were checked using Cronbach’s alpha test, which returned 0.761 to determine the validity and reliability of the Delphi data collection instrument (Tavakol and
Dennick, 2011; Taber, 2018). Likewise, as Rousseaux and Gad (2013) noted, the Mann-Whitney U test was used to compare the perceptions of the expert panellists in academic and professional practices in validating the identified critical factors.
RESULTS
Respondents Demographic Information The demographic information of the fifteen expert panellists involved in the Delphi process (see Table 1). The study findings show that the experts’ high- est academic qualifications, 46.66% (7) with doctorate degrees and 53.66% (8) with master’s degrees, completed the Delphi study process in the first and second rounds. The panellist’s designations in the construction indus- try include 46.66% (7) lecturers in the public and private HEI and 53.66% (8) construction industry professionals with designations such as contractors 20.00%, consultants 13.33%, government agencies 13.33% and director of physical planning 6.66% (comprising architect, builders, engineers, and quantity surveyors). The study findings further indicate that nine had 10– 15 years of experience, four had 16–20 years of experience, one had 21–25 years of experience, and only one expert panel member had 6–10 years of experience. The demographic information set minimum criteria upon which panellists were drawn for the Delphi study met a minimum of 5 points criteria for inclusion of experts and were deemed fit for the study.
Table 1. Respodent’s demographic information.
Table available in the original PDF paper.
Demographic information Frequency (n = 15) Percentage (%) Highest academic qualification Doctor of Philosophy (Ph.D.) 7 46.66% Master of Science degree 8 53.66% Total 15 100% Designation Lecturers 7 46.66% Consultants 2 13.33% Government agency 2 13.33% Contractors 3 20.00% Director of Physical Planning 1 6.67% Total 15 100% Years of experience 1–5 - - 6–10 1 6.66% 11–15 9 60.00% 16–20 4 26.66% 21–25 1 6.67% Above 25 years - - Total 15 100% Professional Affiliations Nigerian Institute of Architects 4 26.66% Nigerian Institute of Building 6 40.00% Nigerian Institute Of Engineers 3 20.00% Nigerian Institute of Quality Surveyors 2 13.34% Total 15 100%
Validating Factors Affecting a National Safety Incentives Policy 55
Respondent’s Perception of the Delphi Forecasted Questions The findings indicate that there is 100% agreement between the experts that the Nigerian national safety incentives policy will be developed for the con- struction industry (see Table 2). Likewise, the findings revealed that 40% of the experts agreed that it would take 6 – 10 years for a national safety incen- tives policy to be developed in Nigeria, 33.33% agreed it would take 11 – 15 years, 13.33% agreed that it would take 16 – 20 years, 13.33% agreed that it would take 0 – 5 years and none of the experts consent if it would take beyond 20 years before a national safety incentives policy will be developed in Nigeria (see Table 2). The findings indicate that 73% of the experts strongly agreed, compared to 27% who agreed, that the lack of a national safety incentives policy affects the effective H&S practices and employee motivation drives in the Nigerian construction industry. The experts’ consensus on this question indicates that NSIP development can drive employee motivation and improve effective H&S practices in the Nigerian construction industry (see Table 2).
Table 2. Respondents perceptions on the Delphi forecasted questions.
Table available in the original PDF paper.
Percentage (%)
Respondent demographic information Frequency (n = 15) Will a national safety incentives policy ever be developed for the Nigerian construction industry?
Yes 15 No - Total
100% - 100% What is the likely timeframe for adopting safety incentive schemes within the Nigerian construction industry?
0 – 5 years 6 – 10 years 11 – 15 years 16 – 20 years Total Strongly agreed Agreed Total
73% 27% 100%
13.33% 40% 33.33% 13.33% 100% Does the lack of a national safety incentive policy for construction organisations affect the Nigerian construction industry’s effective H&S practices and employee motivation drives?
Delphi Study Round One Result Round one of thept Delphi iterations sought to determine the consensus of the panellists and validate the identified critical factors affecting the NSIP development. Ten (10) of the fifteen (15) identified variables were validated as critical factors affecting the NSIP development in Nigeria. Four (4) of the factors had a very high impact (VHI: 9.00–10.00), which are: weak insti- tutional framework, OSH agency’s corrupt practices, stakeholders’ absence in policy development, ineffective H&S code of practice, and political influ- ence OSH enforcement agency, while six (6) variables had a high impact (HI: 7.00–8.99), which are: insufficient government budget for OSH agency, inad- equate regulatory framework, ineffective OSH policy enforcement, absence of national safety incentive vision, the insufficient government budget for OSH agency and ineffective OHS policies, and the remaining five (5) vari- ables recorded a medium impact (MI: 5.00–6.99), which are: absence of continuity in governance, conflicting government policies, ineffective logis- tics for the OSH agency, OSH enforcement personnel skills shortage and bad governance.
Delphi Study Round Two Result The outcome of the second round of the Delphi study establishes consensus among the panellists in validating the identified critical factors affecting the NSIP development (see Table 3). Twelve (12) of the fifteen (15) identified variables were validated as critical factors affecting the NSIP development in Nigeria. Six (6) of the factors had a very high impact (VHI: 9.00–10.00), which are: weak institutional framework, OSH agency’s corrupt practices, stakeholders’ absence in policy development, Absence of national safety incentive vision, insufficient government budget for OSH agency, ineffec- tive H&S code of practice, and political influence OSH enforcement agency, while six (6) variables had a high impact (HI: 7.00–8.99), which are: insuffi- cient government budget for OSH agency, inadequate regulatory framework, ineffective OSH policy enforcement, ineffective OHS policies, absence of con- tinuity in governance, and conflicting government policies, and the remaining three (3) variables recorded a medium impact (MI: 5.00–6.99), which are: ineffective logistics for the OSH agency, OSH enforcement personnel skills shortage and bad governance. Furthermore, the Mann–Whitney U test was conducted to determine the significant difference in the experts’ opinions between the two expert panellist groups (academic and industry profes- sional practice designations). According to Pallant (2005), a p-value > 0.05 indicates a not statistical difference in group opinion; in contrast, a p- value ≤0.05 indicates an imbalance or statistical difference in the group opinion. Two of the fifteen variables, namely, the OSH agency’s corrupt practices 0.014 p-values ≤0.05 and ineffective logistics for the OSH agency 0.032 p-value ≤0.05 indicate a statistical difference in the experts’ opinions from the fifteen identified critical factors affecting the NSIP development (see Table 3). Hence, the study findings from the Delphi study’s second round indicated no variability in the experts’ opinions in academic and industry professional practice.
Table 3. Delphi second-round outcome.
Table available in the original PDF paper.
IQD Mann-Whitney
Barriers to Safety Incentives Design
Median (M)
Mean (x)
Ranking SD (σx)
Z P-value 9 8.73 1 0.96 1.00 −0.42 0.673
Weak institutional framework
9 8.67 2 0.82 0.50 −2.15 0.032
OSH agency’s corrupt practices
9 8.53 3 0.99 1.00 −1.32 0.186
Stakeholders’ absence in policy development
9 8.47 4 0.99 1.00 −0.06 0.952
Absence of a national safety incentive vision
8 8.40 5 0.91 1.00 −1.15 0.250
Insufficient government budget for OSH agency
9 8.40 6 1.06 1.00 −1.56 0.118
Ineffective H&S code of practice
9 8.33 7 1.18 1.00 −1.90 0.057
Political Influence OSH enforcement agency
(Continued)
Validating Factors Affecting a National Safety Incentives Policy 57
Table 3. Continued
Table available in the original PDF paper.
IQD Mann-Whitney
Barriers to Safety Incentives Design
Median (M)
Mean (x)
Ranking SD (σx)
Z P- value 8 8.27 8 1.03 1.00 −0.72 0.469
Inadequate regulatory framework
8 8.20 9 1.15 1.00 −0.96 0.336
Ineffective OSH policy enforcement
8 8.00 11 1.41 1.00 −0.12 0.902
Ineffective OHS policies 8 8.13 10 1.13 1.00 −0.78 0.437 Absence of continuity in governance
A strong consensus was reached for twelve (12) factors with the IQD scores ≤1.00. Thus, the twelve (12) validated factors critically affected the development of a national safety incentives policy in the Nigerian construc- tion industry. The study finding is consistent with Wilde (2011) and Jiang et al. (2019), who affirmed that factors such as policies guiding goal setting and performance indicators affect the construction industry in developing countries to design and implement safety incentives effectively. The six (6) factors with very high impact values (VHI: 9:00–10.00) align with Kheni and Braimah (2014) and Boadu et al. (2021), who attributed the critical fac- tors affecting the national safety incentive policy construction industry to the non-availability-of-comprehensive-health and safety policies to address safety incentive design and implementation. The study findings on the six (6) factors that had had a high impact (HI: 7.00–8.99) agree with Ditlopo et al. (2013), who noted that bad governance, inadequate regulatory frame- work, and inadequate resources to meet the policy pre-conditions critically affect incentive policy development and implementation. Likewise, the study findings support Ghasemi et al. (2015) submission that a lack of policy devel- opment, conflicting government policies, and a lack of annual review and evaluation of safety incentive policy are critical factors affecting national safety incentive policy development and implementation.
CONCLUSION
The study adopted the Delphi technique to validate critical factors affecting NSIP development in developing countries, using Nigeria as a case study. Fif- teen expert panellists were drawn from academic and professional practice in the Nigerian construction industry. The study expert panellists strongly agreed that a national safety incentives policy should be developed for the Nigerian construction industry, with likely timeframes of 6 – 10 years to this time. A strong consensus was reached, establishing that the lack of a national safety incentive policy critically affects effective H&S practices and
employee motivation drives in the Nigerian construction industry. Likewise, a strong consensus was reached using the Delphi technique, validating twelve of the fifteen identified factors that critically affect the development of a national safety incentives policy in the Nigerian construction industry. Hence, the study recommends that in developing a national safety incentives pol- icy for the Nigerian construction industry, construction stakeholders should guide against the following factors: weak institutional framework, occupa- tional safety and health agency’s corrupt practices, stakeholders’ absence in policy development, insufficient government budget allocation for occupa- tional H&S agency, ineffective H&S code of practice, absence of national safety incentive vision, political influence on occupational safety and health enforcement agency, inadequate regulatory framework, ineffective occupa- tional safety and health policy enforcement, and ineffective occupational safety and health policies. This study concluded by calling for a standalone national safety incentive policy that will holistically support the implemen- tation of safety incentives within the construction industry, considering the identified critical factors. The study is limited to selected professionals who are architects, builders, engineers, and quantity surveyors with academic and professional practice experience in Southwestern Nigeria. Hence, further study could adopt a mixed method (qualitative and quantitative) to compare the findings from this study using a larger sample size of stakeholders in the Nigerian construction industry.
REFERENCES
Ahmed, I., Faheem, A. (2021). How effectively do safety incentives work? A randomised experimental investigation. Safety and Health at Work, 12(1), 20–27. Alfandi, A. M., Alkahsawneh, M. S. (2014). The Role of the Incentives and Reward
System in Enhancing Employee’s Performance” A Case of Jordanian Travel and Tourism Institutions”. International Journal of Academic Research in Business and Social Sciences, 4(4), 326. Ameyaw, E. E., Hu, Y., Shan, M., Chan, A. P. C., Le, Y. (2016), “Application of Delphi method in construction engineering and management research: A quanti- tative perspective”, Journal of Civil Engineering and Management, Vol. 22, No. 8, pp. 991–1000. Armstrong, M., Taylor, S. (2014). Armstrong’s Handbook of Human Resource
Practice (10th ed.). London: Ashford Colour Press Ltd. Boadu, E. F., Wang, C. C., Sunindijo, R. Y. (2021), Challenges for occupational health and safety enforcement in the construction industry in Ghana. Construction Economics and Building, 21(1), 1–21. Boadu, E. F., Wang, C. C., Sunindijo, R. Y., (2020), Characteristics of the construc-
tion industry in developing countries and its implication for health and safety; an exploratory study in Ghana. International Journal of Environmental Research and Public Health, [e-journal] 17(11), 4110. https://doi.org/10.3390/ijerph17114110. Chan, A. P. C., Yung, E. H. K., Lam, P. T. I., Tam, C. M., Cheung, S. O. (2001), “Application of Delphi method in selection of procurement systems for con- struction projects”, Construction Management and Economics, Vol. 19, No. 7, pp. 699–718.
Validating Factors Affecting a National Safety Incentives Policy 59
Choi, T. N., Chan, D. W., Chan, A. P. (2012), Potential difficulties in applying the Pay for Safety Scheme (PFSS) in construction projects. Accident Analysis and Prevention, 48, 145–155. Dambisya, Y., Dambisya, Y. (2007). A review of non-financial incentives for health
worker retention in East and Southern Africa. Training and Research Support Centre. EQUINET Discussion Paper 44: University of Limpopo and EQUINET: Harare. Ditlopo, P., Blaauw, D., Rispel, L., Thomas, S., Bidwell, P. (2013). Policy implementation and financial incentives for nurses in South Africa: A case study on the occupation-specific dispensation. Global health action, 6(1), 19289. Evans, M., Farrell, P. (2021), “Barriers to integrating building information mod-
elling and lean construction practices on construction mega-projects: A Delphi study”, Benchmarking: An International Journal, Vol. 28, No. 2, pp. 652–669, doi: 10.1108/BIJ-04-2020-0169. Eyiah, A. K., Kheni, N. A., Quartey, P. D., 2019. An Assessment of Occupational Health and Safety Regulations in Ghana: A Study of the Construction Industry. Journal of Building Construction and Planning Research, [e-journal] 7, pp. 11–31. https://doi.org/10.4236/jbcpr.2019.72002 Gerhart, B. (2017), Incentives and pay for performance in the workplace. In Advances
in motivation science (Vol. 4, pp. 91–140). Elsevier. Ghasemi, F., Mohammadfam, I., Soltanian, A. R., Mahmoudi, S., Zarei, E. (2015).
Surprising incentive: an instrument for promoting the safety performance of construction employees. Safety and health at work, 6(3), 227–232. Giel, B., Issa, R. (2016), “Framework for evaluating the BIM competencies of facilities owners”, Journal of Management in Engineering, Vol. 32, No. 1, pp. 1063–1067, doi: 10.1061/(ASCE) ME.1943–5479.0000378. Goodrum, P. M. and Gangwar, M. (2004), Safety Incentives - A study of their
effectiveness in construction, Professional Safety, 24–34. Haas, E. J., Yorio, P. (2016). Exploring the state of health and safety management system performance measurement in mining organizations. Safety Science, 83, 48–58. doi: 10.1016/j.ssci.2015.11.009. Hilmarsson, S. T., Rikhardsson, P. (2011). The evolution of motivation and incentive systems research: A literature review. Available online: http://dx.doi.org/10.2139/ssrn.1965646. Howell, S. and Kemp, C. (2005), “Defining early number sense: a participatory
Australian study”, Journal of Educational Psychology. 25, (5), 555–571. Iipinge, S., Dambisya, Y. M., Loewenson, R., Chimbari, M., Ndetei, D., Munga, M., Lugina, H. (2009). Policies and incentives for health worker retention in east and southern Africa: learning from country research. Harare: University of Namibia, Training and Research Support Centre, University of Limpopo, EQUINET, ECSA- HC, EQUINET Discussion Paper 78 EQUINET: Harare. Ikuabe, M., Aigbavboa, C. O., Anumba, C., Oke, A. E. (2023). Perfor- mance measurement indicators influential to the espousal of cyber-physical sys- tems for facilities management–a Delphi approach. Construction Innovation. doi: 10.1108/CI-09-2022-0230. Jiang, W., Luo, L., Wu, Z., Fei, J., Antwi-Afari, M. F., Yu, T. (2019), An investigation
of the effectiveness of prefabrication incentive policies in China. Sustainabil- ity, 11(19), 5149. Kheni, N. A., and Braimah, C. (2014). Institutional and regulatory frameworks for health and safety administration: A study of the construction industry of Ghana. International Refereed Journal of Engineering and Sciences, 3(2), 24–34.
Kiguhe, M. B. (2013). The Role of Motivation in Enhancing Employees’ Performance in The Public Sector Organizations in Tanzania: The Case of Immigration Department (Master dissertation, Mzumbe University). Laitinen, H., Vuorinen, M., Simola, A., Yrjänheikki, E. (2013). Observation-based
proactive OHS outcome indicators–the validity of the Elmeri+ method. Safety Science, 54, 69–79. Mahamadu, A., Mahdjoubi, L., Booth, C., Manu, P. Manu, E. (2019), “Building information modelling (BIM) capability and delivery success on construction projects”, Construction Innovation, 19 (2), 170–192, doi: 10.1108/CI-03-2018- 0016. Nasa, P., Jain, R., Juneja, D. (2021). Delphi methodology in healthcare research:
how to decide its appropriateness. World Journal of Methodology, 11(4), 116. doi: 10.5662/wjm.v11.i4.116. Ogunbayo, B. F., Aigbavboa, C., Thwala, W. D. (2023). A Maintenance Management Framework for Municipal Buildings in Developing Economies. Taylor and Francis. Ogunde, A. O., Dafe, O. E., Akinola, G. A., Ogundipe, K. E., Oloke, O. C., Ademola,
S. A., Olaniran, H. F. (2017), Factors militating against prompt delivery of con- struction projects in Lagos megacity, Nigeria: Contractors’ perspective. Mediter- ranean Journal of Social Sciences, 8(3), 233. Ogundipe, K. E., Ogunde, A., Olaniran, H. F., Ajao, A. M., Ogunbayo, B. F., Ogundipe, J. A. (2018), Missing gaps in safety education and practices: aca- demic perspectives. In International Journal of Civil Engineering and Technology (IJCIET), 9(1), 273–289. Ogundipe, K. E., Aigbavboa C., Ogunbayo, B. F. (2023a). Incentives Budget Plan-
ning: Significant Attributes in Designing Safety Incentives Framework in the Construction Industry. Proceedings of the International Conference on Engineer- ing and Innovative Technology Theme: Innovation and Creativity for Sustainable Development 19th–21st September 2023. Ogundipe, K. E., Ogunbayo, B. F., Aigbavboa, C. (2023b). A Review of Barriers to Safety Incentives Design and Implementation in the Construction Industry. Pro- ceedings of the 13th Engineering, Project, and Production Management (EPPM) Conference, 29th November – 1st December 2023, Massey University, New Zealand). Ogundipe, K. E., Aigbavboa, C. & Ogunbayo, B. F. (2023c). A Review of Applicable
Approaches to Safety incentives Design in the Construction Industry. Proceed- ings of the International Conference on Engineering and Innovative Technology Theme: Innovation and Creativity for Sustainable Development 19th – 21st September 2023. Ogwueleka, A. C. (2015). Evaluation of incentive mechanisms on performance-based contracting systems in South Africa and Nigeria (Doctoral dissertation, University of Pretoria). Oloke, O. C., Oni, A. S., Babalola, D., Ojelabi, R. A. (2017). Incentive package,
employee’s productivity and performance of real estate firms in Nigeria. European Scientific Journal, 13(11), 246–260. Rousseaux, C. G., Gad, S. C. (2013). Statistical assessment of toxicologic pathology studies. Haschek and Rousseaux’s Handbook of Toxicologic Pathology, 893–988. Taber, K. S. (2018). The use of Cronbach’s alpha when developing and report-
ing research instruments in science education. Research in science education, 48, 1273–1296.
Validating Factors Affecting a National Safety Incentives Policy 61
Tavakol, M., Dennick, R. (2011). Making sense of Cronbach’s alpha. International journal of medical education, 2, 53. Taylor, F. W. (2003). Scientific management. (Vol. 1), Routledge. Tongo, C. I. (2011). Incentive factors affecting the productivity of public servants in
Ogun State: evidence from Ado-Ota Local Government Area. IFE PsychologIA: An International Journal, 19(2), 1–27. Wilde, G. J. S. (2011). Safety incentives programmes. Encyclopedia of Occupational Health and Safety. Available online: https://www.iloencyclopaedia.org/p art-viii-12633/safety-programs/item/993-safety-incentive-programmes. Accessed September 6, 2022. Zulkefli, F. A., Ulang, N. M., Baharum, F. (2014). Construction health and safety:
Effectiveness of safety incentive programme. In SHS Web of conferences. 11, p. 01012. EDP Sciences.
LISTED IN THE AHFE DIGITAL BOOKSTORE CATALOGUE
Explore the complete digital volume
Sustainable Construction in the Era of the Fourth Industrial Revolution
Read this individual research paper free through the original publisher, or explore the full digital proceedings book.
ISBN 978-1-964867-25-0
Explore this ISBN in the AHFE Bookstore ↗Listed in the July 2026 bookstore catalogue; search by ISBN to confirm current availability · Digital book purchase optional